In MRP, system nervousness is caused by:


A) management's attempt to continually respond to minor changes in production requirements.
B) the use of the lot-for-lot approach.
C) management's marking part of the master production schedule as "not to be rescheduled."
D) the use of phantom bills of material.
E) management's attempt to evaluate alternative plans before making a decision.

F) A) and B)
G) A) and C)

Correct Answer

verifed

verified

When safety stock is deemed absolutely necessary, the usual policy is to build it into (increase) the inventory requirements within the MRP logic.

A) True
B) False

Correct Answer

verifed

verified

Consider the following product structure. Fifteen units of Product A are needed. How many units of B, C, D, and E are needed? Consider the following product structure. Fifteen units of Product A are needed. How many units of B, C, D, and E are needed?

Correct Answer

verifed

verified

Item B: 15(2) = 30 units; Item...

View Answer

A(n) ________ is a bill of material for components, usually subassemblies, that exist only temporarily; they are never inventoried.

Correct Answer

verifed

verified

phantom bi...

View Answer

An order for 50 units of Product A and 60 of B has been placed. There are currently 25 units of Product B on hand. Each A requires 2 units of Part C; each B requires 5 units of C. There are 160 units of C available. What are the net requirements for C?


A) 115
B) 175
C) 240
D) 690
E) 700

F) D) and E)
G) A) and E)

Correct Answer

verifed

verified

Time fences divide the segment of the master schedule that can be revised from the section that is "not to be rescheduled."

A) True
B) False

Correct Answer

verifed

verified

Enterprise resource planning (ERP) :


A) seldom requires software upgrade or enhancement.
B) does not integrate well with functional areas other than operations.
C) is inexpensive to implement.
D) automates and integrates the majority of business processes.
E) all of these

F) B) and D)
G) D) and E)

Correct Answer

verifed

verified

Low-level coding means that:


A) a final item has only a few levels in the BOM structure.
B) the code being used is the code for the lowest level in the BOM structure.
C) a component item is coded at the lowest level at which it appears in the BOM structure.
D) the top level of the BOM is below level zero and that BOMs are not organized around the finished product.
E) the lowest-paid staff member in the production department performs the coding.

F) A) and B)
G) A) and C)

Correct Answer

verifed

verified

Each R requires 3 of component S and 3 of material A; each S requires 3 of part T. The lead time for assembly of R is 1 week. The lead time for the manufacture of S is 2 weeks. The lead time for material A is 1 week. The lead time for the procurement of T is 4 weeks. Construct the time-phased product structure.

Correct Answer

verifed

verified

A(n) ________ is a list of quantities of components, ingredients, and materials required to make a product.

Correct Answer

verifed

verified

bill of ma...

View Answer

If the explosion of the bill of material tells MRP how much of each part is needed, how does MRP learn when each of these parts is needed?

Correct Answer

verifed

verified

Timing is established with the time-phas...

View Answer

The supply-chain systems that result from using ERP in the hospitality industry are called efficient consumer response (ECR) systems.

A) True
B) False

Correct Answer

verifed

verified

Which of the following is NOT a key benefit of MRP?


A) increased quality
B) better response to customer orders
C) faster response to market changes
D) improved utilization of facilities and labor
E) reduced inventory levels

F) A) and B)
G) A) and D)

Correct Answer

verifed

verified

Because MRP provides such a clean structure for dependent demand, it has evolved as the basis for ________.

Correct Answer

verifed

verified

enterprise...

View Answer

Which MRP lot-sizing technique should be considered to be the goal (i.e., the technique of choice under ideal conditions) ?


A) Wagner-Whitin
B) EOQ
C) lot-for-lot
D) POQ
E) Silver-Meal

F) A) and E)
G) A) and B)

Correct Answer

verifed

verified

Clancy's Motors has the following demand to meet for custom manufactured fuel injector parts. The holding cost for that item is $2 per month and each setup costs $80. Lead time is 0 months. Calculate the planned order releases using: (a) the EOQ technique, and (b) the POQ technique. What are the costs of each plan, including the holding cost of any inventory left over after month 7? Clancy's Motors has the following demand to meet for custom manufactured fuel injector parts. The holding cost for that item is $2 per month and each setup costs $80. Lead time is 0 months. Calculate the planned order releases using: (a) the EOQ technique, and (b) the POQ technique. What are the costs of each plan, including the holding cost of any inventory left over after month 7?

Correct Answer

verifed

verified

(a) The monthly holding cost = $2/month
...

View Answer

Firms making many different final products use ________ to facilitate production scheduling.


A) planning bills
B) modular bills
C) phantom bills
D) overdue bills
E) gross requirements bills

F) D) and E)
G) A) and E)

Correct Answer

verifed

verified

Consider the following product structure. Forty units of Product A are needed. How many units of B, C, D, E, F, and G are needed? Consider the following product structure. Forty units of Product A are needed. How many units of B, C, D, E, F, and G are needed?

Correct Answer

verifed

verified

Item B: 40(2) = 80 units; Item...

View Answer

Reduced inventory levels and faster response to changes in demand are both benefits of MRP.

A) True
B) False

Correct Answer

verifed

verified

By convention, the top level in a product structure is designated level 0.

A) True
B) False

Correct Answer

verifed

verified