Filters
Question type

Study Flashcards

The operations manager of a body and paint shop has five cars to schedule for repair. He would like to minimize the throughput time to complete all work on these cars. Each car requires body work prior to painting. The estimates of the times required to do the body paint work on each are as follows:  Car  Body Work  (hrs)   Paint  (hrs)   A 102 B 54 C 75 D 36 E 17\begin{array} { l c c } \text { Car } & \begin{array} { c } \text { Body Work } \\\text { (hrs) }\end{array} & \begin{array} { c } \text { Paint } \\\text { (hrs) }\end{array} \\\hline \text { A } & 10 & 2 \\\text { B } & 5 & 4 \\\text { C } & 7 & 5 \\\text { D } & 3 & 6 \\\text { E } & 1 & 7\end{array} What is the throughput time for the optimal schedule?


A) 24 hours
B) 25 hours
C) 26 hours
D) 28 hours
E) 50 hours

F) A) and B)
G) C) and E)

Correct Answer

verifed

verified

Which sequencing rule is designed specifically to minimize job tardiness?


A) S/O
B) EDD
C) FCFS
D) SPT
E) LPT

F) C) and E)
G) A) and B)

Correct Answer

verifed

verified

Using the cost information given in the following table, assign work crews to jobs so that total cost is minimized.  Job ABC Crew 1$874296931258\begin{array}{ c}\quad\quad\quad\text { Job }\\\begin{array}{rcc}&\mathrm{A} & \mathrm{B} & \mathrm{C} \\\hline\text { Crew }1& \$ 8 & 7 & 4 \\2&9 & 6 & 9 \\3&12 & 5 & 8\end{array}\end{array}

Correct Answer

verifed

verified

blured image_TB2513_00...

View Answer

Given the following data for jobs awaiting processing at a manufacturing cell in which jobs are first processed by machine A, then by machine B:  Process Time (Hours)  Job  Center A  Center B W45X66Y12Z52\begin{array} { c } \quad\quad\quad{ \text { Process Time (Hours) } } \\\begin{array} { l c c } \text { Job } & \text { Center A } & \text { Center B } \\\hline \mathrm { W } & 4 & 5 \\\mathrm { X } & 6 & 6 \\\mathrm { Y } & 1 & 2 \\\mathrm { Z } & 5 & 2\end{array}\end{array} In developing the sequence which will minimize throughput time, what is the initial job to be placed in the schedule sequence?

Correct Answer

verifed

verified

There are three jobs to be done and three resources with which to do them. Each resource will take a specific time to do each job, as shown in the following table:  Machine  Job  A  B  C 169424433874\begin{array} { l c c c } && { \text { Machine } } \\\text { Job } & \text { A } & \text { B } & \text { C } \\\hline 1 & 6 & 9 & 4 \\2 & 4 & 4 & 3 \\3 & 8 & 7 & 4\end{array} Can an optimum assignment be made after the row and column reductions?

Correct Answer

verifed

verified

The SPT priority rule always results in the lowest average completion time.

A) True
B) False

Correct Answer

verifed

verified

Which of the following is not a measure for judging the effectiveness of a schedule sequence?


A) average number of jobs at the work center
B) total number of jobs at the work center
C) average completion (flow) time
D) average job tardiness
E) total number of work centers per job

F) B) and E)
G) A) and E)

Correct Answer

verifed

verified

Refer to the following data for jobs waiting to be processed at a single work center (jobs are shown in order of arrival):  Job  Processing Time ( days ) Due Date  (days from now) A22 B56C610D34E48\begin{array} { l c c } \text { Job } & \begin{array} { c } \text { Processing Time } \\( \text { days } )\end{array} & \begin{array} { c } \text { Due Date } \\\text { (days from now) }\end{array} \\\hline \mathrm { A } & 2 & 2 \\\mathrm {~B} & 5 & 6 \\\mathrm { C } & 6 & 10 \\\mathrm { D } & 3 & 4 \\\mathrm { E } & 4 & 8\end{array} What is the schedule sequence using the earliest due date priority rule?

Correct Answer

verifed

verified

A Gantt chart is a basic scheduling tool that works best for high-volume systems.

A) True
B) False

Correct Answer

verifed

verified

Loading is the determination of which work centers should perform which jobs.

A) True
B) False

Correct Answer

verifed

verified

Based on the cost information given in the following table, which set of job-machine pairs reflects the minimum-cost solution using the Assignment method?  Machine  A  B  C  Job 1 $60023643240\begin{array}{c} \quad\quad\quad\quad\quad{\text { Machine }} \\\begin{array}{rrrr} & \text { A } & \text { B } & \text { C } \\\text { Job 1 } & \$ 6 & 0 & 0 \\2 &3 & 6 & 4 \\3 & 2 & 4 & 0\end{array}\end{array}


A) 1-B, 2-A, 3-C
B) 1-A, 2-B, 3-C
C) 1-C, 2-A, 3-B
D) 1-B, 2-C, 3-A
E) 1-C, 2-B, 3-A

F) A) and E)
G) D) and E)

Correct Answer

verifed

verified

Given the following data for jobs awaiting processing at a manufacturing cell in which jobs are first processed by machine A, then by machine B:  Process Time (Hours)  Job  Center A  Center B W45X66Y12Z52\begin{array} { c } \quad\quad\quad{ \text { Process Time (Hours) } } \\\begin{array} { l c c } \text { Job } & \text { Center A } & \text { Center B } \\\hline \mathrm { W } & 4 & 5 \\\mathrm { X } & 6 & 6 \\\mathrm { Y } & 1 & 2 \\\mathrm { Z } & 5 & 2\end{array}\end{array} When does idle time occur at machine B for the optimum schedule?

Correct Answer

verifed

verified

1 hour at the outset...

View Answer

There are four resources and four jobs to be done. The time required for each resource to do each job is as follows:  Job (Hours)   Resource ABCD15877249593698747669\begin{array} { c } \quad \quad \quad \quad { \text { Job (Hours) } } \\\begin{array} { l c c c c } \text { Resource } & \mathrm { A } & \mathrm { B } & \mathrm { C } & \mathrm { D } \\\hline 1 & 5 & 8 & 7 & 7 \\2 & 4 & 9 & 5 & 9 \\3 & 6 & 9 & 8 & 7 \\4 & 7 & 6 & 6 & 9\end{array}\end{array} What is the optimal assignment of resources to jobs?


A) 1 to A; 2 to C; 3 to B; 4 to D
B) 1 to B; 2 to D; 3 to C; 4 to A
C) 1 to C; 2 to B; 3 to A; 4 to D
D) 1 to D; 2 to B; 3 to C; 4 to A
E) 1 to A; 2 to C; 3 to D; 4 to B

F) A) and B)
G) A) and D)

Correct Answer

verifed

verified

Which of the following is not usually a characteristic of successful high-volume systems?


A) smooth workflow through the system
B) customized output
C) rapid repair of breakdowns
D) minimal quality problems
E) reliable supply schedules

F) C) and D)
G) A) and E)

Correct Answer

verifed

verified

The owner/operator of the local franchise of Handyman, Inc., has four jobs to do today, shown in the order they were received:  Job  Processing  Due  Time (hrs)   (hrs from now)  W44X35Y22Z11\begin{array} { l c c } \text { Job } & \text { Processing } & \text { Due } \\&\text { Time (hrs) } & \text { (hrs from now) } \\\hline \mathrm { W } & 4 & 4 \\\mathrm { X } & 3 & 5 \\\mathrm { Y } & 2 & 2 \\\mathrm { Z } & 1 & 1\end{array} If he uses the shortest processing time first priority rule to schedule these jobs, what will be the average number of jobs in his shop today?


A) 0
B) 1
C) 2
D) 3
E) 4

F) A) and E)
G) C) and D)

Correct Answer

verifed

verified

Job X arrived at work center Q at noon. At 2 p.m. that same day X was begun. X left work center Q at 3:15 p.m. that same day. X's flow time, in minutes, was:


A) 195.
B) 120.
C) 75.
D) 60.
E) Cannot be determined.

F) A) and C)
G) C) and D)

Correct Answer

verifed

verified

When operations are often bottlenecked, additional planned idle time will improve the throughput in those areas.

A) True
B) False

Correct Answer

verifed

verified

Refer to the following data for jobs waiting to be processed at a single work center (jobs are shown in order of arrival):  Job  Processing Time ( days ) Due Date  (days from now) A22 B56C610D34E48\begin{array} { l c c } \text { Job } & \begin{array} { c } \text { Processing Time } \\( \text { days } )\end{array} & \begin{array} { c } \text { Due Date } \\\text { (days from now) }\end{array} \\\hline \mathrm { A } & 2 & 2 \\\mathrm {~B} & 5 & 6 \\\mathrm { C } & 6 & 10 \\\mathrm { D } & 3 & 4 \\\mathrm { E } & 4 & 8\end{array} What is the schedule sequence using the first come, first served priority rule?

Correct Answer

verifed

verified

In theory of constraints scheduling, the __________ refers to the schedule and the __________ refers to inventory used to ensure that the bottleneck is never idle.


A) rope; drum
B) drum; rope
C) drum; buffer
D) buffer; drum
E) buffer; rope

F) C) and E)
G) A) and D)

Correct Answer

verifed

verified

The president of a consulting firm wants to minimize the total number of hours it will take to complete four projects for a new client. Accordingly, she has estimated the time it should take for each of her top consultants-Charlie, Betty, Johnny, and Rick-to complete any of the four projects, as follows:  Project (Hours)   Consultant  A  B  C  D  Charlie 13161113 Betty 11151418 Johnny 15221215 Rick 17171222\begin{array} { c } \quad \quad \quad \quad \quad { \text { Project (Hours) } } \\\begin{array} { l c c c c } \text { Consultant } & \text { A } & \text { B } & \text { C } & \text { D } \\\hline \text { Charlie } & 13 & 16 & 11 & 13 \\\text { Betty } & 11 & 15 & 14 & 18 \\\text { Johnny } & 15 & 22 & 12 & 15 \\\text { Rick } & 17 & 17 & 12 & 22\end{array}\end{array} In how many different ways can she assign these consultants to these projects?


A) 4
B) 8
C) 16
D) 24
E) 256

F) A) and B)
G) B) and C)

Correct Answer

verifed

verified

Showing 21 - 40 of 134

Related Exams

Show Answer