Filters
Question type

Study Flashcards

The following table contains information about five jobs waiting to be processed at work center number three.  Job  Processing  Time (hrs)   Hours Until  Due a1415 b1020c1818 d216e421\begin{array} { l c c } \text { Job } & \begin{array} { c } \text { Processing } \\\text { Time (hrs) }\end{array} & \begin{array} { c } \text { Hours Until } \\\text { Due }\end{array} \\\hline \mathrm { a } & 14 & 15 \\\mathrm {~b} & 10 & 20 \\\mathrm { c } & 18 & 18 \\\mathrm {~d} & 2 & 16 \\\mathrm { e } & 4 & 21\end{array} The sequence that would result using the SPT rule is:


A) e-b-c-d-a.
B) c-a-b-e-d.
C) a-d-c-e-b.
D) d-e-b-a-c.
E) e-d-b-a-c.

F) B) and D)
G) A) and D)

Correct Answer

verifed

verified

What is the optimum job sequence for the jobs listed below using Johnson's rule?  Processing time (hrs)   Job  Center 1  Center 2 d1323e2313f1618 g2017\begin{array}{l}\text { Processing time (hrs) }\\\begin{array} { c c c } \text { Job } & \text { Center 1 } & \text { Center 2 } \\\hline \mathrm { d } & 13 & 23 \\\mathrm { e } & 23 & 13 \\\mathrm { f } & 16 & 18 \\\mathrm {~g} & 20 & 17\end{array}\end{array}


A) e-g-f-d
B) d-g-f-e
C) d-f-g-e
D) e-d-f-g
E) f-e-d-g

F) C) and D)
G) A) and B)

Correct Answer

verifed

verified

Eva, the owner of Eva's Second Time Around Wedding Dresses, currently has five dresses to be altered, shown in the order in which they arrived:  Job  Processing  Time (hrs)   Due  (hrs from now)  V35 W11X49Y23Z57\begin{array} { l c c } \text { Job } & \begin{array} { c } \text { Processing } \\\text { Time (hrs) }\end{array} & \begin{array} { c } \text { Due } \\\text { (hrs from now) }\end{array} \\\hline \mathrm { V } & 3 & 5 \\\mathrm {~W} & 1 & 1 \\\mathrm { X } & 4 & 9 \\\mathrm { Y } & 2 & 3 \\\mathrm { Z } & 5 & 7\end{array} If Eva uses the earliest due date first (EDD) priority rule to schedule these jobs, what will be the average job tardiness?


A) 2 hours
B) 2.2 hours
C) 2.33 hours
D) 2.4 hours
E) 3 hours

F) None of the above
G) C) and D)

Correct Answer

verifed

verified

Given the following data for jobs awaiting processing at a manufacturing cell in which jobs are first processed by machine A, then by machine B:  Process Time (Hours)  Job  Center A  Center B W45X66Y12Z52\begin{array} { c } \quad\quad\quad{ \text { Process Time (Hours) } } \\\begin{array} { l c c } \text { Job } & \text { Center A } & \text { Center B } \\\hline \mathrm { W } & 4 & 5 \\\mathrm { X } & 6 & 6 \\\mathrm { Y } & 1 & 2 \\\mathrm { Z } & 5 & 2\end{array}\end{array} What is the sequence which will minimize throughput time?

Correct Answer

verifed

verified

Scheduling in service systems often takes the form of: (I) appointment systems. (II) reservation systems. (III) makespan systems.


A) I only
B) II only
C) I and II only
D) III only
E) I, II, and III

F) All of the above
G) C) and E)

Correct Answer

verifed

verified

Which of the following is the last step in the capacity/scheduling chain?


A) product planning
B) process planning
C) capacity planning
D) aggregate planning
E) scheduling

F) A) and E)
G) None of the above

Correct Answer

verifed

verified

Which of the following is not an example of a high-volume system?


A) aircraft manufacturing
B) magazine printing
C) petroleum refining
D) waste treatment
E) commercial donut baking

F) B) and D)
G) A) and D)

Correct Answer

verifed

verified

Given the following data for jobs awaiting processing at a manufacturing cell in which jobs are first processed by machine A, then by machine B:  Process Time (Hours)  Job  Center A  Center B W45X66Y12Z52\begin{array} { c } \quad\quad\quad{ \text { Process Time (Hours) } } \\\begin{array} { l c c } \text { Job } & \text { Center A } & \text { Center B } \\\hline \mathrm { W } & 4 & 5 \\\mathrm { X } & 6 & 6 \\\mathrm { Y } & 1 & 2 \\\mathrm { Z } & 5 & 2\end{array}\end{array} In developing the sequence that will minimize throughput time, where in the schedule sequence should job W be placed?

Correct Answer

verifed

verified

Given the following data for jobs awaiting processing at a manufacturing cell in which jobs are first processed by machine A, then by machine B:  Process Time (Hours)  Job  Center A  Center B W45X66Y12Z52\begin{array} { c } \quad\quad\quad{ \text { Process Time (Hours) } } \\\begin{array} { l c c } \text { Job } & \text { Center A } & \text { Center B } \\\hline \mathrm { W } & 4 & 5 \\\mathrm { X } & 6 & 6 \\\mathrm { Y } & 1 & 2 \\\mathrm { Z } & 5 & 2\end{array}\end{array} What is the throughput time for the optimum schedule?

Correct Answer

verifed

verified

In a task assignment situation, in how many different ways can five jobs be assigned to five machines?


A) 1
B) 5
C) 25
D) 120
E) 3,125

F) A) and D)
G) A) and E)

Correct Answer

verifed

verified

In an assignment model where there are fewer jobs than resources:


A) dummy jobs are needed to solve the problem.
B) dummy resources are needed to solve the problem.
C) the problem cannot be solved using an assignment model.
D) the problem will have multiple optimum solutions.
E) the simplex method must be used to solve the problem.

F) A) and B)
G) B) and D)

Correct Answer

verifed

verified

Which of the following is not an assumption of priority rules?


A) The set of jobs is known: no new jobs arrive after processing begins.
B) Setup time is independent of processing sequence.
C) Finite loading is assumed.
D) Processing times are deterministic.
E) No machine breakdowns are assumed.

F) B) and C)
G) A) and E)

Correct Answer

verifed

verified

Infinite loading and finite loading are two major approaches used to load work centers.

A) True
B) False

Correct Answer

verifed

verified

The president of a consulting firm wants to minimize the total number of hours it will take to complete four projects for a new client. Accordingly, she has estimated the time it should take for each of her top consultants-Charlie, Betty, Johnny, and Rick-to complete any of the four projects, as follows:  Project (Hours)   Consultant  A  B  C  D  Charlie 13161113 Betty 11151418 Johnny 15221215 Rick 17171222\begin{array} { c } \quad \quad \quad \quad \quad { \text { Project (Hours) } } \\\begin{array} { l c c c c } \text { Consultant } & \text { A } & \text { B } & \text { C } & \text { D } \\\hline \text { Charlie } & 13 & 16 & 11 & 13 \\\text { Betty } & 11 & 15 & 14 & 18 \\\text { Johnny } & 15 & 22 & 12 & 15 \\\text { Rick } & 17 & 17 & 12 & 22\end{array}\end{array} For the optimal schedule, what is the total number of hours it will take these consultants to complete these projects?


A) 53 hours
B) 46 hours
C) 50 hours
D) 61 hours
E) 54 hours

F) A) and E)
G) A) and D)

Correct Answer

verifed

verified

Showing 121 - 134 of 134

Related Exams

Show Answer