Filters
Question type

Study Flashcards

Use the following cost information to calculate the direct labor rate and efficiency variances and indicate whether they are favorable or unfavorable. Ā ActualĀ costsĀ andĀ quartities:Ā Ā DirectĀ laborĀ costĀ incurredĀ $360,000Ā DirectĀ laborĀ hoursĀ usedĀ 20,000Ā hoursĀ Ā UnitsĀ producedĀ 45,000Ā unitsĀ Ā tandardĀ costsĀ andĀ quantities:Ā Ā DirectĀ laborĀ rateĀ perĀ hourĀ $16.50Ā HoursĀ toĀ produceĀ oneĀ unitĀ 0.5Ā hoursĀ \begin{array}{lc} \text { Actual costs and quartities: } \\\text { Direct labor cost incurred } & \$ 360,000 \\\text { Direct labor hours used } & 20,000 \text { hours } \\\text { Units produced } & 45,000 \text { units } \\\text { tandard costs and quantities: } & \\\text { Direct labor rate per hour } & \$ 16.50 \\\text { Hours to produce one unit } & 0.5 \text { hours }\end{array}

Correct Answer

verifed

verified

None...

View Answer

A cost variance equals the sum of the quantity variance and the price variance.

A) True
B) False

Correct Answer

verifed

verified

Actual fixed overhead for Kapok Company during March was $92,780.The flexible budget for fixed overhead this period is $89,000 based on a production level of 5,000 units.If the company actually produced 4,200 units what is the fixed overhead volume variance for March?


A) $3,780 favorable
B) $18,020 unfavorable
C) $14,240 unfavorable
D) $3,780 unfavorable
E) $14,240 favorable

F) All of the above
G) C) and D)

Correct Answer

verifed

verified

A _______________________ contains relevant information that compares actual results to planned activities.

Correct Answer

verifed

verified

A standard that takes into account the reality that some loss usually occurs with any process under normal application of the process is known as a __________________ standard.

Correct Answer

verifed

verified

This information comes from the records of Dina Co. for the current period: Actual costs and quantities: Ā DirectĀ materialsĀ usedĀ 38,000Ā feetĀ @$$6.20Ā perĀ footĀ Ā DirectĀ laborĀ hoursĀ usedĀ 50,660Ā hoursĀ Ā DirectĀ laborĀ rateĀ perĀ hourĀ $16Ā FactoryĀ overheadĀ $211,60025,000Ā unitsĀ wereĀ producedĀ duringĀ theĀ period.Ā Ā StandardĀ costsĀ andĀ quantitiesĀ perĀ unit:Ā 1.5ft.@$6.10Ā perĀ ft.Ā DirectĀ materialsĀ 2Ā hoursĀ @Ā $17Ā perĀ hourĀ Ā DirectĀ laborĀ \begin{array} { l l } \text { Direct materials used } & 38,000 \text { feet } @ \$ \$ 6.20 \text { per foot } \\ \text { Direct labor hours used } & 50,660 \text { hours } \\ \text { Direct labor rate per hour } & \$ 16 \\ \text { Factory overhead } & \$ 211,600 \\ 25,000 \text { units were produced during the period. } & \\ & \\ \text { Standard costs and quantities per unit: } & 1.5 \mathrm { ft } . @ \$ 6.10 \text { per } \mathrm { ft } . \\ \text { Direct materials } & 2 \text { hours @ } \$ 17 \text { per hour } \\ \text { Direct labor } & \end{array} Factory overhead (based on budgeted production of 24,500 units) Variable overhead $2.25/\$ 2.25 / direct labor hour Fixed overhead $1.95/\quad \$ 1.95 / direct labor hour -Make the necessary general journal entries to record the above standard and actual costs, and all variances.

Correct Answer

verifed

verified

\[\begin{array} { l r r }
\text { Goods...

View Answer

A cost variance is the difference between actual cost and standard cost.

A) True
B) False

Correct Answer

verifed

verified

The difference between the actual cost incurred and the standard cost is called the:


A) Flexible variance.
B) Price variance.
C) Cost variance.
D) Controllable variance.
E) Volume variance.

F) B) and C)
G) C) and D)

Correct Answer

verifed

verified

A process of examining the differences between actual and budgeted costs and describing them in terms of the amounts that resulted from price and quantity differences is called:


A) Cost analysis.
B) Flexible budgeting.
C) Variable analysis.
D) Cost variable analysis.
E) Cost variance analysis.

F) D) and E)
G) A) and B)

Correct Answer

verifed

verified

A company's flexible budget for 36,000 units of production showed variable overhead costs of $54,000 and fixed overhead costs of $50,000.The company actually incurred total overhead costs of $95,300 while operating at a volume of 32,000 units.What is the controllable variance?

Correct Answer

verifed

verified

* $54,000 variable o...

View Answer

A company's flexible budget for 48,000 units of production showed variable overhead costs of $72,000 and fixed overhead costs of $64,000.The company incurred overhead costs of $122,800 while operating at a volume of 40,000 units.The total controllable cost variance is:


A) $1,200 favorable
B) $1,200 unfavorable
C) $13,200 favorable
D) $13,200 unfavorable
E) $15,200 favorable

F) A) and E)
G) None of the above

Correct Answer

verifed

verified

Cost variances are ignored under management by exception.

A) True
B) False

Correct Answer

verifed

verified

Actual fixed overhead for a company during March was $97,612.The flexible budget for fixed overhead this period is $88,000 based on a production level of 5,500 units.If the company actually produced 4,300 units, what is the fixed overhead spending variance for March?


A) $9,612 favorable
B) $1,200 unfavorable
C) $28,812 unfavorable
D) $9,612 unfavorable
E) $28,812 favorable

F) B) and C)
G) A) and E)

Correct Answer

verifed

verified

A company established a direct material standard of 2 pounds of material at a cost of $6 per pound for unit produced.During August the company produced 6,000 units of product; 10,000 pounds of direct material that cost $6.50 per pound were used in the production process.Compute the direct material price variance for August.


A) $5,000 unfavorable
B) $12,000 unfavorable
C) $5,000 favorable
D) $12,000 favorable
E) $7,000 favorable

F) A) and B)
G) None of the above

Correct Answer

verifed

verified

Bartels Corp.produces woodcarvings.It takes two hours of direct labor to produce a carving.Bartels' standard labor cost is $12 per hour.During August, Bartels produced 10,000 carvings and used 21,040 hours of direct labor at a total cost of $250,376.What is Bartels' labor rate variance for August?


A) $10,376 unfavorable
B) $2,104 unfavorable
C) $2,104 favorable
D) $12,480 unfavorable
E) $ 12,480 favorable

F) A) and B)
G) B) and E)

Correct Answer

verifed

verified

A company established a direct material standard of 2 pounds of material at a cost of $6 per pound for unit produced.During August the company produced 6,000 units of product.10,000 pounds of direct material which cost $6.50 per pound were used in the production process.Compute the direct material quantity variance for August.


A) $5,000 unfavorable
B) $12,000 unfavorable
C) $5,000 favorable
D) $12,000 favorable
E) $7,000 favorable

F) C) and D)
G) A) and C)

Correct Answer

verifed

verified

Presented below are terms preceded by letters (a)through (j)and followed by a list of definitions (1)through (10).Enter the letter of the term with the definition, using the space preceding the definition. (a)Cost variance (b)Volume variance (c)Price variance (d)Quantity variance (e)Standard costs (f)Controllable variance (g)Fixed budget (h)Flexible budget (i)Variance analysis (j)Management by exception __________ (1)The difference between the total budgeted overhead cost and the overhead cost that was allocated to products using the predetermined fixed overhead rate. __________ (2)A planning budget based on a single predicted amount of sales or production volume; unsuitable for evaluations if the actual volume differs from the predicted volume. __________ (3)Preset costs for delivering a product, component, or service under normal conditions. __________ (4)A process of examining the differences between actual and budgeted sales or costs and describing them in terms of the amounts that resulted from price and quantity differences. __________ (5)The difference between actual and budgeted sales or cost caused by the difference between the actual price per unit and the budgeted price per unit. __________ (6)A budget prepared based on predicted amounts of revenues and expenses corresponding to the actual level of output. __________ (7)The difference between actual and budgeted cost caused by the difference between the actual quantity and the budgeted quantity. __________ (8)The combination of both overhead spending variances (variable and fixed)and the variable overhead efficiency variance. __________ (9)A management process to focus on significant variances and give less attention to areas where performance is close to the standard. __________ (10)The difference between actual cost and standard cost, made up of a price variance and a quantity variance.

Correct Answer

verifed

verified

(1)b (2)g (3)e (4)i ...

View Answer

______________________ are preset costs for delivering a product or service under normal conditions.

Correct Answer

verifed

verified

Cheshire, Inc., allocates fixed overhead at a rate of $18 per direct labor hour.This amount is based on 90% of capacity or 3,600 direct labor hours for 6,000 units.During May, Cheshire produced 5,500 units.Budgeted fixed overhead is $66,000, and overhead incurred was $67,000. Required: Determine the volume variance for May.

Correct Answer

verifed

verified

(3,600 DLH/6,000 uni...

View Answer

When the actual cost of direct materials used exceeds the standard cost, the company must have experienced an unfavorable direct materials price variance.

A) True
B) False

Correct Answer

verifed

verified

Showing 21 - 40 of 177

Related Exams

Show Answer